On Friday, May 27, 2022, water and sewer connections begin for the development at 8047 Floral Avenue. As part of the construction, one section of the lane will be closed on Floral Avenue between Oakton and Brown Streets and on June 3, Floral Avenue between Oakton and Brown Streets will be closed to through traffic from 7 a.m. to 4 p.m. to ensure the safety of both motorist and construction workers. Weather permitting, the construction work on Floral Avenue is expected to be complete by Tuesday, June 8.
A detour will be in place at both Oakton and Brown Streets for southbound and northbound traffic on Floral Avenue, with all traffic routed to Laramie Avenue. For more information, please contact the Engineering Division at 847/933-8231.